Asia sees fewer naphtha cracker maintenance schedules in 2019

Asia sees fewer naphtha cracker maintenance schedules in 2019

Title

Naphtha Ethylene Propylene

Available in

Jadwal maintenance shutdown cracker naphtha di pasar Asia dengan jumlah lebih sedikit di tahun 2019, dan tidak ada laporan akan terjadi maintenance shutdown di Thailand dan Singapore saat laporan ini dipublikasikan. 

Dibawah ini jadwal maintenance major operator di Asia: 

Plant Name

Location

C2 Capacity

C3 Capacity

Shutdown Date

Shutdown Duration

Borouge 3

Abu Dhabi, UAE

1,500,000

-

Jan-19

60 days

Hanwha Total Petrochemical

Daesan, South Korea

1,100,000

860,000

27-Mar-19

45 days

LG Chem

Daesan, South Korea

940,000

450,000

Early March 19

30 days

KPIC

Onsan, South Korea

800,000

500,000

Apr-19

30 days

YNCC

Yeochun, South Korea

860,000

450,000

May

30 days

Idemitsu

Chiba, Japan

414,000

-

Q2 19

30 days

Keiyo Ethylene

Chiba, Japan

768,000

400,000

Q3 19

30-45 days

Formosa

Mailiao No 2

1,030,000

515,000

Q3 19

30-45 days

Chandra Asri Petrochemical

Cilegon, Indonesia

840,000

470,000

Q3 2019

30 days

Petronas Chemicals Olefins

Kerteh, Malaysia

600,000

-

Aug 19

50-60 days

Lotte Chem

Daesan, South Korea

1,000,000

500,000

Dec-19

28 days

www.commoplast.com

 

 

 

 

 

 

Shutdown lebih fokus di negara Korea Selatan di tahun ini dengan Hanwha Total Petrochemical berencana ekspansi kapasitas produksi sebanyak 310.000 ton/tahun ke 1.41 juta ton dibandingkan produksi saat ini. 

Country

Indonesia
Malaysia
Singapore
Thailand