Asia sees fewer naphtha cracker maintenance schedules in 2019
Asia sees fewer naphtha cracker maintenance schedules in 2019

Naphtha Ethylene Propylene
Jadwal maintenance shutdown cracker naphtha di pasar Asia dengan jumlah lebih sedikit di tahun 2019, dan tidak ada laporan akan terjadi maintenance shutdown di Thailand dan Singapore saat laporan ini dipublikasikan.
Dibawah ini jadwal maintenance major operator di Asia:
Plant Name |
Location |
C2 Capacity |
C3 Capacity |
Shutdown Date |
Shutdown Duration |
Borouge 3 |
Abu Dhabi, UAE |
1,500,000 |
- |
Jan-19 |
60 days |
Hanwha Total Petrochemical |
Daesan, South Korea |
1,100,000 |
860,000 |
27-Mar-19 |
45 days |
LG Chem |
Daesan, South Korea |
940,000 |
450,000 |
Early March 19 |
30 days |
KPIC |
Onsan, South Korea |
800,000 |
500,000 |
Apr-19 |
30 days |
YNCC |
Yeochun, South Korea |
860,000 |
450,000 |
May |
30 days |
Idemitsu |
Chiba, Japan |
414,000 |
- |
Q2 19 |
30 days |
Keiyo Ethylene |
Chiba, Japan |
768,000 |
400,000 |
Q3 19 |
30-45 days |
Formosa |
Mailiao No 2 |
1,030,000 |
515,000 |
Q3 19 |
30-45 days |
Chandra Asri Petrochemical |
Cilegon, Indonesia |
840,000 |
470,000 |
Q3 2019 |
30 days |
Petronas Chemicals Olefins |
Kerteh, Malaysia |
600,000 |
- |
Aug 19 |
50-60 days |
Lotte Chem |
Daesan, South Korea |
1,000,000 |
500,000 |
Dec-19 |
28 days |
|
|
|
|
|
Shutdown lebih fokus di negara Korea Selatan di tahun ini dengan Hanwha Total Petrochemical berencana ekspansi kapasitas produksi sebanyak 310.000 ton/tahun ke 1.41 juta ton dibandingkan produksi saat ini.